|
|
|
|
|
|
Decision Session – Executive Member for Transport
|
21 March 2023 |
Report of the Assistant Director for Environment, Transport and Planning |
Active Travel Programme Update
Summary
1. This report provides an update on the progress of the Active Travel Programme and asks the Executive Member to note this update.
2. An update on the recent Active Travel Fund Tranche 4 funding bid submission to Active Travel England is also included within this report, and the Executive Member is asked to note this update.
3. This report also provides a Project Outline document defining the “A19 Active Travel Phase 1” scheme and asks for a decision from the Executive Member to approve this Project Outline.
4.
Additionally, this report provides a
summary of a recent consultation undertaken on the Riverside Path
(Jubilee Terrace – Scarborough Bridge) scheme and seeks a
decision to approve the proposed next steps for the scheme.
This section
should set out clearly the author’s recommendation for a
particular option and the reasons why.
5.
The Executive is asked to:
1)
Note the update on the progress of
the Active Travel Programme contained within this report.
Reason: To provide
information to the public and the Member on the current status of
the Active Travel Programme.
2) Note the update contained within this report covering the recent ATF4 bid submission.
Reason: To provide information to the public regarding the request for funding submitted to Active Travel England.
3)
Approve the
“A19 Phase 1 Interventions” Project Outline (Option
1).
It should be noted that a decision on the implementation of the
crossing is not being sought at this time. A further public
decision on the proposals will be presented after feasibility work
has been completed.
Reason: To agree the scope of the project, to ensure it is aligned
with stakeholder expectations.
4)
Note the results of the Riverside
Path Consultation, the initial feasibility work undertaken by Aecom
and the current funding gap.
Reason: To understand the options
for improving the route and the priorities for the local
residents.
5) Approve the progression of Option 2 to deliver the scheme on a phased basis commencing with the higher priority affordable items (lighting & CCTV) and undertake further development work within the current budget.
Reason: Progressing with Phase 1 of the path upgrade (lighting and CCTV) allows progress to be made on-site whilst further work is undertaken on the feasibility of the full scheme.
Active Travel Programme Update
Background
6.
This section contains an update on
the progress of the Active Travel Programme.
7.
A summary of the progress of all
schemes within the programme can be found as Annex C to this
report. Additional information on key projects is highlighted
below.
Consultation
8.
Each individual scheme within the
programme is subject to its own consultation process. An indication
of the status of consultations for each scheme can be found in
Annex C.
Analysis
Wheldrake / Heslington Active Travel Path Update
9.
In the November 2022 Executive
Session (Background Paper 2), the Wheldrake / Heslington Active
Travel Path scheme was paused pending further funding. There was
however a decision to:
“Officers are now instructed to enter
discussions with landowners and bring to a member decision
session.”
10.
This instruction has been carried
out and letters have been sent to relevant landowners to start
these discussions.
11.
At the time of writing, a response
has been received from one of the landowners. The details of this
confidential communication cannot be shared in this report, however
the broad substance of the response was that the landowner was open
to further discussion on the detail of the scheme.
12. As noted elsewhere within this report, this scheme has formed part of CYC’s recent bid to Active Travel England for funding support to undertake development work. Should this request for funding be successful, the scheme will be progressed and feasibility work will be resumed. Discussion with land owners will continue.
A19 Shipton Road Active Travel Corridor
Scheme
13.
In the November 2022 Executive
Session (Background Paper 2), the A19 Shipton Road Active Travel
Corridor scheme was split into 2 phases.
14.
The first phase of works relates to
smaller scale interventions identified by the local community and
is named “A19 Shipton Road Phase 1 Interventions” on
the programme.
15.
This report seeks approval for the
scope of this scheme, and this information can be found in the
project outline document attached as Annex E.
16.
The second phase of the scheme
relates to the full corridor works and retains the same objectives
and scope as previously identified. This phase of the works has
been paused pending further funding.
17. Feasibility work has been completed on the full corridor scheme, however consultation cannot start until funding is identified to progress the scheme.
City Centre North South Cycle Route
18.
In the November 2022 Executive
Meeting a decision was made to confirm funding for this scheme as
part of the Phase 1 works, and to award a contract for the
progression of feasibility and design work.
19.
This contract has now been awarded
and the feasibility work has begun. It is expected that the first
stage of this feasibility work will be ready for a public
consultation in June 2023.
20.
A separate ward scheme is also
underway to consider improvements to pedestrian routes at the
Aldwark / Ogleforth junction. A raised table at the junction has
been considered, however a road safety audit has indicated that
this is not a viable solution. Alternative solutions are currently
being explored.
City Centre Cycle Parking Improvements
21.
A Cycle Parking Design Standard has
been created to inform the principles on which the scheme design
should be based. This design standard is currently part of a
targeted consultation process that is due to complete by March
27th 2023. This consultation is also seeking input on
proposed locations for new cycle parking infrastructure.
22.
This feedback will be taken into
account during the ongoing feasibility work that is due to be
completed in April 2023.
23. Following the completion of this feasibility work, a full public consultation will be undertaken on specific proposals. The current aim is to carry out this consultation in June 2023, followed by a public decision in approximately August 2023.
Active Travel Fund Tranche 4 Bid
Background
24.
On the 6th of February
2023 Active Travel England (ATE) invited Local Authorities to
submit bids for funding support as part of the ‘Active Travel
Fund Tranche 4’ opportunity. The letter received from ATE is
attached as Annex A to this report.
25.
The deadline for submissions of bids
to this fund was the 24th of February 2023.
26.
Prior to the official announcement
of the funding opportunity on the 6th of February, ATE
confidentially contacted Local Authorities with advanced notice of
the intention to announce the fund, providing sufficient
information to start formulating a bid. This initial communication
was sent to Local Authorities on the 10th of January
2023 and has been followed up by further briefings and Q&A
sessions from ATE.
27.
Unfortunately, the timescales
provided were not sufficient to allow an opportunity for a public
consultation or a public decision to be made on the content of the
bid, or indeed on the choice of schemes to be included within the
bid.
28.
This report summarises the content
of the bid that was submitted to ATE on 24th February;
lays out the rationale for the choice of schemes that were
included; and covers the implications for York’s Active
Travel Programme.
29.
The submitted bid can be found in
Annex B. A summary of the scheme contained and omitted from the bid
can be found in Annex D.
Consultation
30.
The timescales available to submit a
bid for funding did not allow an opportunity to undertake a public
consultation.
31. The bid was created by officers in consultation with the Executive Member for Transport and was supported by the Leader of the Council.
Analysis
32.
In the November 2022 Executive
Meeting (Background Paper 2), a decision was made to prioritise the
Active Travel Programme into 2 phases. Phase 1 projects were
assigned sufficient funding to proceed, whereas those projects
prioritised as Phase 2 were paused pending further funding. It was
highlighted that future funding opportunities would likely become
available from ATE and other sources.
33.
It should be noted that this current
funding opportunity is not seen as the only available potential
source of funding for Phase 2 schemes. If a Phase 2 scheme was not
included within this bid, alternative funding opportunities will
still be explored.
34.
The ‘indicative
allocation’ for York is £367,698, with Local Authorities
encouraged to bid for more than this amount, up to 300% of this
value, which is £1,103,094. The total amount of all schemes
contained with our bid exceeds this amount, at £2,961,000.
This was a deliberate choice and reflects the level of ambition
that is present on matters of Active Travel, including a desire to
improve York’s self-assessment level. Despite this approach,
there is still a practical upper limit on the amount that York can
realistically bid for, and therefore it is not sensible to include
a bid for every potential active travel scheme currently
identified.
Rationale for deciding which schemes to include in the
bid
35.
There was a requirement within the
bid to differentiate between schemes that are ‘for
construction’, and those that are ‘for
development’, with construction-ready schemes being more
likely to attract funding. As such, the primary factor that
determined if a scheme should be included within the bid was an
evaluation of how well progressed the scheme was, and therefore how
deliverable the scheme was likely to be.
36.
Another primary factor that was
considered when deciding which schemes to include in the bid was
the specific eligibility criteria identified by ATE. For example,
schemes that were identified as scoring well on specific LTN 1/20
assessment were more likely to be successful and were therefore
prioritised within the bid.
37.
York’s draft Local Cycling and
Walking Infrastructure Plan (LCWIP) was also considered when
determining which schemes to include within the bid. Ideally those
schemes listed within the LCWIP should be prioritised, however this
consideration was taken into account with reference to the need to
bid for construction-ready schemes.
38.
Attention was also given to the
guidance provided by ATE in the bid invitation letter (Annex A),
specifically ‘Table 1 – Types of scheme proportionate
to local authority capability levels’ and ‘Table 2
– Examples of the sort of schemes that are more / less likely
to attract funding’.
Schemes included within the bid
39.
People Streets at Ostman Road
– This scheme is currently ‘shelf-ready’ in terms
of deliverability. Feasibility work has been completed,
consultation has been completed, a public decision has been
obtained on the solution to be implemented, and the commissioning
of detailed design is underway. The only significant barrier to
delivery currently present is the absence of sufficient funding to
construct the scheme.
40.
All relevant details of this scheme
can be found in Background Paper 3.
41.
Manor Lane / Shipton Road –
This scheme has completed Feasibility work and is due to go through
public consultation and public decision. Feasibility work indicates
that this scheme is likely to be readily deliverable with few
significant obstacles likely to emerge.
42.
The current budget assigned to this
scheme is only sufficient to deliver approximately half of the
scheme, hence the opportunity to apply for additional government
support to delivery the full benefits.
43.
A full description of the proposed
scheme can found in Background Paper 1. The aforementioned
Feasibility report will be released as part of the upcoming
consultation and public decision process.
44.
Jubilee Terrace to Scarborough
Bridge Riverside Path – Due to the fact that a significant
amount of feasibility work has already been undertaken, this scheme
is a good fit for construction funding support.
45.
It is noted that the funding
required to deliver this scheme is significant, and in excess of
the ‘indicative value’ assigned to CYC by ATE for ATF4
support.
46.
Tang Hall Lane / Foss Islands Path
– Similarly, this scheme has progressed through feasibility
work and there is a certain level of confidence that the scheme is
deliverable on the ground.
47.
A consultation and decision session
is still due to be undertaken, and this will be able to progress if
sufficient funding support is obtained.
48.
Development Bids – 5 schemes
were included within the bid for ‘development’ support.
This means that funding was sought to undertake feasibility work
for the scheme, but not for full construction.
49.
These 5 schemes include ‘Haxby
to Strensall Village Active Travel Route’, ‘Wheldrake /
Heslington Path’, ‘Acomb Road Scheme’,
‘Fulford Road / Frederick House’ and ‘Monkgate
Roundabout’
50.
Details of all the bid submissions
can be found within the bid itself, at Annex
B.
A19 Phase 1 Active Travel Scheme
Background
51.
In the November 2022 Executive
Meeting (Background Paper 2) a decision was made to split the
‘A19 Shipton Road Cycle Route’ scheme into 2 phases.
The first phase, ‘A19 Shipton Road Phase 1
Interventions’ was assigned £100k of funding.
52.
This report proposes a scope of
works for this scheme and asks for a decision to approve the
Project Outline document found in Annex E to this report.
53. This decision will ensure that officers are progressing a scheme that aligns with the Executive Members expectations.
Consultation
54.
The Project Outline was created in
consultation with the Executive Member and input from Councillor
Smalley. Councillor Smalley’s comments on the attached
document were in support of the proposals. He indicated that it
fits what had been discussed with local residents, and agreed with
a suggestion to future proof the crossing so that it can be turned
into a Toucan in the future if needed.
55.
The Project Outline was then
circulated to Councillors for the Rawcliffe and Clifton Without
Ward, and Parish Councillors for the Clifton Without Parish Council
and Rawcliffe Parish Council.
56.
Feedback from Parish Councillor
Hagon indicated that “Nearly everyone wanted the junction - very few
said it wasn’t needed”.
57.
Further feedback from Councillor
Hagon indicated that there was some debate within the community
about the preferred location of the crossing, either north or south
of the Fylingdale Avenue junction.
58.
Comments supporting locating the
crossing to the north of the junction included:
- “School children will use it more and dog walker too if
it’s there”
- “It won’t be directly in front of residential
property”
- “It will help cars exit Fylingdale Avenue, slowing down
speeding traffic”
- “if to the south, it
will be harder to turn right out of Fylingdale Avenue, and it will
be near the bus stop which might cause accidents as cars try to
overtake stationary buses”
59.
Comments supporting locating the
crossing to the south of the junction included:
- “The bus stop to town and Aldi are that way, so it will be
used more by putting it there”
- “The footpath to the north is too narrow”
60.
Other comments included “How
far will the crossing be from the junction”, “A speed
reduction on Shipton Road would affect my opinion” and
“what about a mini roundabout on the junction to slow traffic
down?”
61.
It should be noted that a decision
on the location of the crossing is not being sought at this time. A
further public decision on the proposals will be presented after
feasibility work has been completed.
62. A public consultation was not undertaken on this project outline, however a public consultation will be undertaken when preliminary design work has been completed.
Analysis
63.
This project aims to improve
pedestrian access across the A19 Shipton Road for people travelling
between Fylingdale Avenue and Northolme Drive in both
directions.
64.
The nearby residential streets,
hospital and other local amenities are located on each side of the
A19, resulting in a pedestrian desire line across this main
arterial route.
65.
Provision of a standalone signalised
pedestrian crossing over the A19 will improve safety, convenience
and amenity of the pedestrian route at this location.
66.
Primary risks to the scheme involve
the requirement to divert utilities, which could significantly
impact scheme costs. This will be considered during the feasibility
stage to effectively manage this risk.
67.
It is unlikely that the scheme
described within the Project Outline will score highly against any
of the assessment criteria within LTN 1/20. This is due to the fact
that the scheme does not contain any cycling infrastructure. This
scheme is primarily intended to serve pedestrian use, as described
within the scheme objectives.
68. Although this is not a cycling scheme, walking is a mode of active travel, and pedestrians are at the top of the Road User Hierarchy. This scheme can therefore be considered a valid use of active travel.
Riverside Path (Jubilee Terrace – Scarborough Bridge)
Background
69.
The riverside path is a key route on
the pedestrian and cycle network connecting the west of the city
from Jubilee Terrace to the city centre and the Scarborough Bridge
river crossing.
70.
Following an initial feasibility
review a public consultation exercise was undertaken in December
2022 and January 2023 to seek feedback from local residents and
users of the riverside path to understand their priorities for any
improvements.
71.
The feasibility study has identified
that a scheme to deliver the aspirations of the community would
cost approx. £2.39m including contingency and risk allowances.
A bid for additional funding has been submitted to Active Travel
England however an announcement is pending. An option for
delivering the highest priority improvements in the short term is
presented in the report.
72.
Upgrades to the cycle and walking
network in the local area will be made as part of the York Central
development, including the introduction of alternative high-quality
routes unaffected by river flooding. However, the importance of the
existing riverside route to residents and cyclists will remain for
residents in the area. The council has acquired the land and set
aside £600K to make improvements to the path.
73.
Consultants were commissioned in
2022 to undertake a feasibility study and assist with a public
consultation exercise. Key areas for consideration include improved
lighting, CCTV, seating, security, widening or segregating the
path, reducing the impact of flooding and surfacing.
74. The initial work has identified a number of potential improvements which have been estimated to have a total cost of £2.39m. This estimate includes significant contingency allowances, for example for flood compensation storage, within the estimates but it is clear that the current allocation is insufficient to deliver the full aspirations of the local community. A bid for £1.758m has recently been submitted to Active Travel England to enable the full scheme to be delivered.
Consultation
75.
Following initial feasibility work a
public consultation exercise was undertaken in December 2022 and
January 2023 to seek feedback from local residents and users of the
riverside path to understand their priorities, concerns about the
existing path and gather feedback on potential options for path
improvements. The feedback received will help shape a detailed
design and inform a planning application for the scheme when
funding is secured.
76. The consultation began on Friday 2 December 2022 and concluded at 11:59pm on Sunday 8 January 2023. Members of the public and stakeholders were asked to submit their comments online at www.york.gov.uk/RiversidePath, or via email or post. There were also two public drop-in events, where attendees could fill out and submit hard copy response forms. These took place at St. Barnabas Church (Jubilee Terrace, Leeman Rd, York, YO26 4YZ) on the dates and times shown below:
a. Saturday 10 December, 10:30am to 3:30pm.
b.
Tuesday 13 December, 12:30pm to
7pm.
77.
The consultation information used on
the website and at the exhibitions is attached at Annex F.
78.
Between 30 and 40 people attended
the exhibitions on each day. A total of 444 consultation responses
were received. This is made up of 441 responses via the online or
hard copy response form, and three detailed response emails. Five
hard copy response forms were received after the close of the
consultation. They are not included in the analysis in the
consultation report, but have been read and considered by the
project team.
79. The consultation report contains a breakdown of the responses, including quantitative and qualitative data identifying common themes. It also includes a brief summary of the type of respondent, including their stated use of the path, frequency of use, as well as other demographic data.
Summary of Consultation
Responses
80.
The detailed results of the consultation are
included in the Consultation Report in Annex F. A summary of the
key items is included in the following paragraphs.
81.
The responses were fairly evenly split across
people who identified as male or female and people who cycled and
walked. Approx. 20% of the respondents indicated that they had a
mental or physical disability.
82.
The path is used for a variety of
purposes with getting to work and leisure being the highest
responses. 83% of the respondents indicated that they strongly
support the plans to improve the path.
83.
There were a variety of areas
identified as needing improvement with lighting, usability during
flood events, the condition of the path and the availability of
space for different users being identified by the most
respondents.
84.
Nearly 100 respondents identified
other areas needing improvement with the most common themes being
maintenance, the underpass under Scarborough Br and the provision
of benches and resting places.
85. When asked to identify their top three priorities lighting, providing more space for pedestrians and cyclists on the existing route, and raising the path to reduce impact of flooding came out the highest.
86.
The results were different between
genders and disabled users but the highest 3 priorities remained
the same. However more female and gender-neutral respondents
identified CCTV/security as a higher priority than male
respondents. More male respondents identified raising the path as a
higher priority than female respondents.
87.
Widening of the path had generally
higher positive support (214) compared to the separate path (132)
but with some respondents identifying concerns about conflict
between users and impact on trees. 75 respondents identified a
clear preference for the separate path option.
88. When asked for whether there were any other items which should be considered maintenance was the most common followed by improvements to the Scarborough Br underpass and flood signage.
Feasibility Study -
Summary
89.
Aecom were commissioned to undertake
a feasibility study investigating potential improvements to the
Riverside Path. The feasibility report is attached as Annex G and
it includes drawings.
90. The feasibility study had the following objectives which were to be reviewed following the consultation phase:
a. Improved Lighting
b. Improved Security – CCTV / Lighting
c. Improved Environment – Including review of NR fence
d. Improved Accessibility – Barrier upgrade
e. Improved Drainage – Surface water drainage
f. Improved Removal of Flood Water / Silt – Drainage / Warping
g. Increased availability of the route (Jubilee Terrace to Scarborough Br / Post Office Lane) during hight river levels.
h. Increased capacity (Width / Layout?) – Consideration of widening existing route or separating peds / cyclists entirely (eg changing existing route to be for cyclists only and providing dedicated pedestrian route closer to the river bank)
i. Delivery without closing the route
j.
Improved Management of Pedestrian /
Cyclist conflicts at Scarborough Bridge arch. Realignment, signage,
barrier arrangements etc.
91. There are two main character areas of the path
a. Jubilee Terrace – 150m length of single carriageway cul-de-sac
b.
Cinder Lane Foot / Cycle Path
– 600m length of approx. 3m segregated path.
92. There are a number of issues and constraints along the path:
a. Flooding at Low Point – route affected on an average of approx. 10 days a year
b. High number of users – over 1000 cyclists and 1500 pedestrians using the route on a daily basis.
c. Inconsistent lighting
d. Lack of CCTV
e. Lack of seating / rest areas
f. Tree line close to the existing path, which could restrict opportunities to widen the path in some locations.
g.
Poor alignment at the Scarborough
Bridge underpass and narrow arch.
93.
A Cycle Level of Service Assessment
(CLoS) was undertaken for the path assessing the route for five key
requirements (cohesion, directness, safety, comfort and
attractiveness). The path has been split into two sections for the
assessment (on carriageway (1A) and off road (1B)).
94. In summary, the existing sections fail to meet the 70% or above threshold specified within the CLoS Audit criteria. Section 1A scores are lower due to lack of continuity, markings / signage and high levels of kerbside activity. Whereas Section 1B scores are lower due to lack of sufficient width for cyclists, poor lighting and surface quality, with the results as follows:
a. Section 1A: 54%
b.
Section 1B:
68%
95. A number of key constraints and risks were identified during the feasibility stage which will require further work during the detailed design stage:
a. Potential impact on flood storage
b. Potential impact on trees of path widening
c. Potential impact on Network Rail Fence
Feasibility Options
Section A – Jubilee
Terrace
96. Proposals within Section A - Jubilee Terrace were identical in either option, with the aims of reducing vehicle dominance through reduction and formalisation of parking, increased conspicuity of the cycle route through signage and road markings strategy, additional wayfinding / flood level signage, speed reduction measures and improved pedestrian crossing facilities.
Section B – Cinder Lane
Path
97. Proposals in Section B – Cinder Lane Path followed two approaches as depicted below:
a. Approach 1 – Widening the existing shared use path
b. Approach 2 – Provision of a separate path over a section of the route
98. Other specific measures identified during the concept / feasibility design process included:
a. Upgrade existing lighting or install new lighting where required (including under Scarborough Bridge)
b. Reduce conflict between pedestrians and cyclists at Scarborough Bridge underpass
c. Install additional low level bollard lighting on a footpath if this approach is taken forward
d. Install CCTV in key locations along the path
e. Raise path level at localised low points (on both sides of Scarborough Bridge)
f. Provide better advance warning systems to let people know when sections of the route are likely to be flooded
g. Additional seating / benches along the path
h. Improved pedestrian crossings to / from St Barnabas Primary School
i.
Introduce Traffic Regulation Orders
to reduce parking space availability on Jubilee Terrace and
reconsider reallocation of road space.
99. A Cycle Level of Service Assessment (CLoS) was undertaken on the options indicating that the assessment would be above the threshold for both approaches:
a. Section 1A – 70%
b. Section 1B – Approach 1: 88%
c. Section 1B – Approach 2: 92%
100.Initial work has been undertaken to understand the options and costs of raising the low section of the path to reduce the number of times a year it is affected by flooding. If the path was raised to a similar level to the Scarborough Bridge underpass then the impact of the flooding could be reduced from approx. 9 days to approx. 3 days a year (based upon the last 10 years of river level data). However, there is the potential need, subject to Environment Agency approval, for flood storage to be provided in the area to compensate for the removal of flood storage volume where the path is raised. Further hydraulic modelling and discussion with the Environment Agency is required before the extent of flood compensation is confirmed.
Cost Estimate
101.Budget cost estimates have been prepared for the approaches identified in the feasibility report.
Element and Potential Phase |
Riverside Path (Scarborough Br to Jubilee
Terrace) |
Cost Estimate |
(inc uplifts & 25% risk) |
||
|
Feasibility Study/Surveys etc. |
£50,000 |
|
|
|
1 |
Whole route Street lighting |
£121,000 |
|
Supplementary CCTV |
£81,000 |
|
Sub Total 1 |
£202,000 |
2 |
Raising of low point (either side of Scarborough Bridge)* approx 250m length, including reconstruction of NR fence (~275m)** |
£683,000 |
|
Estimated cost of compensatory flood storage (tbc) *** |
£277,000 |
|
Sub Total 2 |
£960,000 |
3 |
Widening of the existing shared use path (west of Element 1)* approx.400m length including reconstruction of remaining NR fence (~125m) |
£752,000 |
|
Estimated cost of compensatory flood storage (tbc) *** |
£270,000 |
|
Sub Total 3 |
£1,022,000 |
4 |
Jubilee Terrace Area |
£154,000 |
|
Sub Total 4 |
£154,000 |
|
GRAND TOTAL Approx. (Sub Totals 1-4 and assuming widening of existing path) |
£2,388,000 |
Analysis
102.There is insufficient funding to deliver the
full community ambition for the path improvements: Funding
available £600k, Cost Estimate approx. £2,390k. Two of
the higher priority items, raising and widening of the path, are
not affordable within the current budgets. The following options
have been considered to progress the project. Note: A bid for
additional funding has been submitted to Active Travel England
which if received in full would enable the full scheme to be
implemented.
103.There is strong support for improvements to the
Riverside Path to enhance the link between the Leeman Rd island
community and the city centre/Scarborough Bridge.
104.Option 2 delivering the scheme on a phased basis
would enable the higher priority affordable items to be delivered
in 23/24 as a first phase subject to planning and approvals with
the remainder progressed when funding is available. The
consultation identified improved lighting as one of the highest
priorities for the route followed by raising the path and widening
the path. CCTV coverage was also supported by a significant
proportion of respondents. It is proposed that these elements of
the scheme would be delivered in line with the priorities
identified if funding was not available to deliver the full scheme.
Subject to detailed design and consideration of the impact on trees
it is proposed to progress a widened path scheme. If funding
becomes available to deliver the full scheme a further report will
be presented to the Executive Member to gain approval for the
layout prior to progressing to implementation. There is a risk that
delivering elements of the overall scheme independently will result
in additional costs and potential abortive work if the full scheme
is delivered at a later date. The design of early phases will be
future proofed as much as possible to minimise these risks.
105.Option 3 would enable the cost of the scheme to
be more accurately established which would help with the submission
of future bids for funding. However, this option would not meet the
aspirations of the community for improvements and would mean some
of the affordable elements would not be delivered and existing
funding allocations would not be used for any immediate benefit for
the residents in the area.
106.Option 4 would not make use of existing funding
allocations and not meet the aspirations of residents in the
area.
107.Option 2 is therefore recommended to be progressed.
108.Option 1 – Approve the “A19 Phase 1 Interventions” Project Outline attached to this report as Annex E.
109.Option 2 – Riverside Path – Deliver
the scheme on a phased basis progressing the higher priority
improvements that can be afforded within the budget available as
phase 1 and developing further phases for delivery when funding is
identified. (Recommended)
Option 2 (costing up to £550k) using the existing funding
would enable, Phase 1 to be progressed. In this option The lighting
would be improved following detailed assessment and the provision
of CCTV would be investigated and delivered if affordable and
permitted. It would also include further development work to be
undertaken to provide more certainty for the flooding and tree
impacts costs. In addition, some of the lower cost elements
identified in the consultation, such as improved signing, would
also be investigated and delivered. It would not be proposed to
deliver the changes to the Jubilee Terrace section in this option
as it was identified as the lowest priority in the
consultation.
Opportunities for further funding to deliver the raising and / or
widening would also be investigated.
110.Option 3 – Riverside Path –
Undertake further design work but delay the delivery of any
improvements until sufficient funding was identified to deliver
some or all of the scheme.
This option (costing approximately £50k) would enable further
design work to be undertaken to provide more cost certainty,
particularly for the flood compensation element. This would
potentially reduce the funding ask for the scheme. However this
option would not deliver any improvements to the area in the short
term.
111.Option 4 – Riverside Path – Do
Nothing
This option would terminate the scheme at this stage recognising
that the funding was insufficient to deliver the full enhancement
for the area.
Council Plan
112.
Delivery of the Active Travel
Programme supports the key Council Objective of “Getting
Around Sustainably” and “Good health and
wellbeing”.
113. The Riverside Path proposals relate well to many of the Council’s key core outcomes, as set out in the Council Plan 2019-23 and the Local Transport Plan.
a. An open and effective council: listening to residents to ensure it delivers the services they want and works in partnership with local communities.
b. A greener and cleaner city: providing improved links to promote sustainable travel
c. Good health and wellbeing: promotion of cycling and walking to improve health and wellbeing of residents
· Financial
The recommended
options outlined in the report are within the allocated capital
budgets. The capital budget for the riverside path is £600k
and element 1 can be delivered within this budget. Further funding
will need to be identified to deliver the other elements. The A19
Phase 1 Interventions project scope is within the £100k budget
allocated for this scheme phase.
· Human Resources (HR)
There are no Human
Resources implications
·
Equalities
The Council needs to take into account the Public Sector Equality Duty under Section 149 of the Equality Act 2010 (to have due regard to the need to eliminate discrimination, harassment, victimisation and any other prohibited conduct; advance equality of opportunity between persons who share a relevant protected characteristic and persons who do not share it and foster good relations between persons who share a relevant protected characteristic and persons who do not share it in the exercise of a public authority’s functions).
An Equalities Impact Assessment has been carried
out and is annexed to this report at Annex H.
· Legal
Procurement
Any proposed works and services will need to be commissioned via a compliant procurement process under the Public Contract Regulations 2015 and the council’s Contract Procedure Rules. The Commercial Procurement team will need to be consulted alongside Legal Services, and the Insurance team so appropriate documents, contracts and processes can be completed. A procurement strategy will be completed to determine the best route to market and to ensure the council is achieving value for money whilst delivering the contract.
Grant funding
Legal Services will carry out a review of any proposed grant funding arrangements and in respect of the UK Subsidy Control Rules (previously State aid) to confirm whether any mitigating actions need to be taken prior to entering into the arrangements.
CCTV
Officers will need to consider the provisions of the General Data Protection Regulations 2018, the Regulation of Investigatory Powers Act 2000 and the Protection of Freedoms Act when deciding where to position CCTV cameras.
· Crime and Disorder
The aim of the recommended option for the
Riverside Path scheme is to improve the safety of local residents,
particularly at night.
·
Information Technology
(IT)
The Riverside
Path scheme will involve connection to the council’s CCTV
network which will be delivered through existing supply contracts
in consultation with the Head of IT.
·
Property
There are no Property implications
Risk Management
114. The Active Travel Programme is managed in line with the Corporate Risk Management Strategy and each individual project is subject to risk management in line with appropriate project management methodologies.
115. ‘The A19 Phase 1 Interventions’ scheme is currently funded from Active Travel England sourced funding. The Project Outline proposed as part of this report describes a project that does not match the commitments made to Active Travel England.
116. There is a risk that Active Travel England will not support the proposed scheme and deem that is not in line with their expectations of what their funding would contribute towards.
117. The implications, should this risk cause materialise, is a potential reduction in future funding support.
118. Contact has been made with ATE to attempt to discuss and address this concern, however this discussion has not yet happened.
119. The key risks for the Riverside Path relate to resolving the funding gap and the extent of the flood compensation requirements. In mitigation Option 2 proposes to phase the project to match the funding available and undertake further work to confirm the requirements for flood compensation storage prior to implementation.
Contact Details
Authors: |
Chief Officer Responsible for the report:
|
|||||||
Christian WoodSmart Transport Programme Manager01904 551 652
Tony Clarke York Central Lead 01904 551 641 |
James GilchristDirector of Environment, Transport and Planning
|
|||||||
Report Approved |
√ |
Date |
[10/03/2023] |
|||||
|
||||||||
|
|
|
|
|||||
Specialist Implications Officer(s)
Financial: Legal: Patrick Looker Cathryn Moore Finance Manager Corporate Business Partner (Legal) 01904 551 633 01904 552 487
|
||||||||
Wards Affected: |
All |
Y |
|
|||||
|
|
|||||||
All
For further information please contact the author of the report |
|
|||||||
Background Papers:
Background
Paper 1 – February 2022 Executive Member Decision Session -
https://democracy.york.gov.uk/ieListDocuments.aspx?CId=738&MId=12734&Ver=4
(Item 48)
Background Paper 2 – November 2022 Executive Meeting Report - https://democracy.york.gov.uk/ieListDocuments.aspx?CId=733&MId=13292&Ver=4 (Item 49)
Background
Paper 3 – November 2022 Executive Member Decision Session
Report (Item 37) -
https://democracy.york.gov.uk/ieListDocuments.aspx?CId=738&MId=13551&Ver=4
Background Paper 4 – July 2022 Executive Member Decision Session – https://democracy.york.gov.uk/mgAi.aspx?ID=62826#mgDocuments
Annex A – ATF4 Bid Invitation Letter
Annex B – Active Travel Fund Tranche 4 Bid
Annex C – Active Travel Programme Summary
Annex D – ATF4 Bid Scheme Summary
Annex E – Project Outline – A19 Shipton Road Phase 1 Interventions
Annex F – Riverside Path Consultation Report
Annex G – Riverside Path Feasibility Report
Annex H – Equalities Impact Assessment
List of Abbreviations Used in this Report
ATE – Active Travel England
DfT – Department for Transport
CYC – City of York Council
ATF4 – Active Travel Fund Tranche 4
LCWIP – Local Cycling and Walking Infrastructure Plan
NR – Network Rail